Safe Work Procedure for Bricklaying: Steps and Controls

Expert workplace safety insights and guidance

• Safety Space Team • Workplace Safety

Ask a site supervisor what's in the bricklaying safe work procedure and the answer is usually a hard hat, safety boots and a high-vis shirt. That's the PPE column. It's the least useful part of the document, and on most jobs it's the only part anyone reads.

Bricks don't hurt people because someone forgot gloves. They hurt people because a pack was stacked at ankle height and lifted three hundred times in a shift, because a housing trestle carried a pallet it was never rated for, because the saw was set up dry and open beside the lunch shed.

A safe work procedure for bricklaying is a planned work method. It should read like a set of decisions already made about this job, so a crew can follow them without guessing who decided what.

Table of Contents

Hazards, Controls and PPE for Bricklaying

Start with the hazard table, because that's the first thing a reviewer checks and the first thing an inspector tests against the site.

HazardWhere it arisesControl to write inPPE
Falls from scaffolds and platformsWorking on scaffolds, mobile platforms and raised edgesFully decked scaffold, guardrails, brick guards, castors locked before accessHarness where the fall control plan requires one
Falling objectsStacking bricks, lifting packs above the work face, tools left on platformsBrick guards, exclusion zone below, tidy stacksSafety helmet
Manual handling strainLifting, carrying and placing bricks, blocks and mortar tubsMaterials positioned in the reach zone, mechanical aids or team lifts for heavy loads, adjustable platform heightGloves and safety footwear
Silica dustDry or power cutting of bricks, blocks and mortarWet cutting or on-tool extraction, isolated cutting area, no dry sweepingRespirator selected by risk assessment and fit tested
Slips, trips and falls at ground levelMortar and brick debris, hoses and leads across work areasDebris removed promptly, leads routed clear, surfaces checked before each shiftSafety footwear
Eye injuryCutting, grinding and mortar splashGuarding on saws, cutting in a designated areaSafety glasses or goggles
Skin contact with mortarMixing and handling wet mortar and cementMixing in a designated area, washing facilities close byWaterproof gloves and long sleeves
Contact with overhead powerlinesScaffold moves, materials handled near overhead linesExclusion zone and powerline clearance check before erection and before each moveNo PPE protects against line contact

Read the table from left to right the way a supervisor works through it on the day: what can hurt someone here, where does it happen, what have we changed about the work, and only then what they wear. The right column gets written first on most templates and it's the one that changes least.

The regulator's own claim data explains why the middle columns matter more. Across 2008–09 to 2012–13, body stressing was the leading mechanism of serious construction claims at 37 per cent, and 47 per cent of those body-stressing claims came from muscular stress while lifting, carrying or putting down objects, according to Safe Work Australia's construction industry profile. Bricklaying is that exposure in its purest form: a brick is picked up, carried and placed hundreds of times a shift, and a mortar tub is worse.

That same profile puts falls, trips and slips second at 28 per cent of serious construction claims, with most caused by same-level falls. Not a scaffolder going over a guardrail. A boot catching a hose, a mortar board left across a doorway, an offcut pile beside the mix station.

The rule worth applying: if a control only tells the worker to be careful, it belongs in training, not in the procedure. The procedure should record what's been changed about the layout, the platform, the tools or the sequence.

New Zealand crews work to the Health and Safety at Work Act 2015 and WorkSafe NZ guidance rather than the Australian WHS Act. The duty holder is still a PCBU and the exposures are identical, so the table transfers without edits. Only the citation on the form changes.

Wet trades borrow from each other here. Melbourne Tiling Services publishes safety-first tiling articles that cover cutting setup, slurry control and housekeeping from a tiler's side of the wall, and most of it applies directly to a brick job.

Scaffold Limits by Fall Height

Most bricklaying procedures say "scaffold to be erected by a competent person" and stop. That tells a supervisor nothing they can check against the platform standing in front of them.

Potential fallScaffold or platformRequirements
Less than 2 mFully decked heavy-duty frame trestleBay length 1.8 m or less; lighter housing scaffolds are not suitable
More than 2 mHeavy-duty modular scaffoldFitted with brick guards
Any height (mobile unit)Mobile scaffoldLevel and plumb, castors locked before access, never moved with anyone on it

The 1.8 m bay and heavy-duty trestle requirement comes from Safe Work Australia's model Code of Practice for construction work. Where bricklaying carries a risk of a fall under 2 m, it specifies a fully decked, heavy-duty frame trestle scaffold with bay lengths of 1.8 m or less. It also warns that lighter scaffolds intended for ordinary housing work are not suitable for heavy-duty activities such as bricklaying. That's the sentence to quote when someone wants to run a brick job off a plasterer's trestle.

Scaffold arrangements must account for the loads from workers, bricks, mortar and equipment. The practical Australian benchmark is no more than 100 bricks per bay or 400 kg of blocks, set out in the Safe Work Australia model construction code. The failure mode is rarely the total. It's distribution: a pallet tipped into one corner of a bay can overload a section of platform while the whole-platform figure still looks acceptable. Spread the load across the bay and write that instruction into the procedure in those words.

Above 4 m, the scaffolder's licence becomes the control. Any scaffold from which a person could fall more than 4 m must be erected, altered and dismantled by a licensed scaffolder, and the site needs a way to check that before the crew climbs.

  • Access: stair or ladder tower, never a climb through the frame.
  • Alterations: prohibited without the scaffolder, including moving a transom to fit a lintel.
  • Inspection: after erection, alteration, impact or severe weather, with the result recorded.

The clause most procedures leave out: who secures the scaffold when the bricklaying crew knocks off. The model code's own example is that bricklaying subcontractors may secure scaffolds by removing access ladders, with the builder and subcontractor consulting, cooperating and coordinating on the control.

Run the pre-start against a scaffold inspection checklist so the result sits in the job file rather than in someone's memory of a Tuesday.

How to Lay Bricks Safely, Step by Step

An infographic showing a nine-step safe work procedure for bricklaying, including safety tips and cost estimates.

A procedure written in operating order gets followed. One written as a list of warnings gets skimmed. The sequence below runs in the order the work happens, and each step carries its own reason, which is what makes it stick on a crew that has heard safety talks before.

  1. Set the work zone first. Mark the exclusion zone below the lifts and walk the sequence with the crew before a trowel comes out. People who know where they stand don't drift under a load.
  2. Check the platform before anyone climbs. Level, plumb, fully decked, guarded and correctly accessed. A mobile unit also stays clear of powerlines, edges and penetrations, with castors locked before access and nobody aboard when it moves.
  3. Stage what the shift needs, not the whole delivery. Bricks, mortar tubs and blocks all count against the platform's load limit. A bay holding four packs is a different structure from a bay holding one.
  4. Route services along the inside line. Hoses and leads crossing the work face go under boots all shift. Run them along the wall side of the deck, away from the access point, and lift offcuts into a bin rather than kicking them aside.
  5. Lift with something other than a back. Mechanical aids or a two-person lift for heavy packs and blocks, named in the procedure along with who supplies the aid.
  6. Work from the deck. Never stand on bricks, a guardrail or an improvised stack of blocks to gain height. That single shortcut accounts for a lot of the fall rate below.
  7. Put materials where the work is. Position stacks to cut repeated twisting, overreaching and long carries. A pallet parked well back from the wall adds a carry to every brick in it.
  8. Clean as you go and recheck at knock-off. The platform the next crew inherits is the one this crew left.

Falls deserve their own number here, because bricklaying sits at height more than most trades. Safe Work Australia reported a construction falls-related serious-claim incidence rate of 2.1 per 1,000 employees in 2010–11, against 0.7 per 1,000 across all industries, three times the overall rate, in its falls from height guidance.

The same failures turn up whenever a bricklaying incident gets investigated: brick guards missing from a loaded bay, castors left unsecured on a mobile unit, a platform stacked past its rated load, a transom shifted to suit the work, or material dropped outside an exclusion zone. Each one maps to a step above, so a supervisor investigating an incident checks the step that failed rather than only the outcome. That is also how the procedure earns its revisions. When a step fails twice, rewrite the step, name the control more precisely and run it again at the next pre-start.

Record the pre-start checks, scaffold inspections, worker sign-on, corrective actions and close-out evidence in the project safety system while the shift is still running. A procedure that lives only on paper proves nothing about the day the incident happened.

Silica Controls for Cutting Bricks and Blocks

"Wear a respirator when cutting" isn't a silica control. It's a purchase order with no verification attached, and it survives in procedures because it's easy to write and impossible to audit.

Cutting, drilling, grinding and polishing brick, concrete and stone can release respirable crystalline silica, and power tools used dry are the worst case, as Safe Work Australia sets out on its silica hazard page. The risk has to be assessed for the actual task, the actual equipment and the actual location, not treated as housekeeping.

Order the controls before naming the respirator

  1. Avoid the cut. Order accurately sized units, prefabricated lintels and coursing that lands on module. Every cut designed out is an exposure that never happens.
  2. Isolate the cutting area. Screens or distance, away from the work face, the tea room and the entry path other trades use.
  3. Wet the cut or capture the dust at the tool. Water topped up, extractor checked and cleaned, hose and shroud fitted.
  4. Stop the dust travelling. No dry sweeping, no compressed air on ledgers, no blower across a finished wall.
  5. Fit the respirator to the person and the risk. Selection by risk assessment, fit testing, facial hair limits, and a cleaning and storage routine that someone owns.
  6. Record it. Who cut, for how long, which control was running, and whether it failed.

An infographic showing silica safety controls, personal equipment, and best practices for cutting bricks and blocks.

There's a nuance in the 2025 model Code of Practice that catches people out: processing controls can apply even where manual tools create, or are reasonably likely to create, respirable crystalline silica exposure. "It's only a hand saw" isn't an exemption. The duty is to eliminate the risk where practicable and otherwise minimise it so far as reasonably practicable, which the national silica guide sets out in full.

Wet cutting technique carries over from tile work, where the same blades run wet all day. The Tiles Mate large tile cutting guide covers setup and scoring on big format material, and the water discipline it describes is the same one a brick saw needs.

Set review triggers rather than relying on an annual review: a new saw, a different block type, a move to a new cutting location, or a rise in cuts per shift. Each morning, confirm the station matches the procedure, photograph the setup for the file, and log it against the SWMS for concrete cutting used on that job. The procedure then answers the three questions that matter after an exposure: who was exposed, which control was in place, and whether it failed.

Manual Handling Controls That Stop Repeat Strain

A lifting technique reminder leaves the crew working around the same awkward layout. A bricklaying procedure must address repeated carrying, bending and reaching before work starts, including strain that develops gradually across shifts.

Safe Work Australia's key WHS statistics show body stressing was the largest mechanism of serious workers' compensation claims in 2022–23, at 45,000 claims or 32.7 per cent, with a median 9.2 weeks lost and A$17,800 paid. The procedure needs controls for that repeated exposure, with clear responsibility for arranging the work.

Design the work, then coach the technique

  • Rotation that changes the demand. Move workers between laying, cutting, mixing and ground-level tasks according to the physical demands involved. Moving someone from laying to carrying can keep the same muscles under load. Name the task changes in the procedure so rotation has a practical purpose.
  • Limits on repositioning. Set how often a pack or mortar tub needs moving, and arrange work fronts to reduce repeated handling. Check the route from the drop point to the wall before placing materials. A convenient delivery location can leave the crew with unnecessary carrying throughout the shift.
  • Adjustable platform height. Plan deck height so the course being laid sits between waist and chest, reducing low-level kneeling and overhead reaching. Keep adjustments within the scaffold's permitted configuration and loading limits. Material placement must work with those limits.
  • Heat, hydration and pace. Build water, shade and rest into the shift plan, and name who checks the arrangements. Allow for the effort of moving materials as well as laying them, particularly when the crew is rushing to finish a lift.

The procedure must assign responsibility for the layout, handling aids and task changes that let workers lift correctly.

What the supervisor can record

Use checks that can be compared across shifts. Record the conditions workers face and the controls available:

  • Distance a pack travels from the drop point to the wall.
  • Deck height at the start of each lift.
  • Whether lift assistance was available and whether it was used.
  • Rest and hydration arrangements for the day.
  • Early discomfort reported at the pre-start, and the response.

Act on discomfort while the task can still be changed. A sore shoulder reported before work gives the supervisor a reason to review carrying, reach height or rotation that morning. Record the adjustment and check whether it helped. Link that action to the manual handling techniques the crew has been trained in, so instruction and working conditions stay aligned.

Toolbox Talk Points and JSA or SWMS Template Fields

A toolbox talk that says something the SWMS doesn't is a defect in both documents. Keep them as two versions of the same plan, one spoken and one recorded.

Toolbox talk, read at the start of the shift

  • The day's task, the sequence, and where the exclusion zone sits.
  • The platform check result and anything that changed overnight.
  • What's staged in each bay and what the load limit is.
  • Who lifts what, and which aid they're using.
  • The cutting method for today and who's wearing which respirator.
  • PPE by task, not one list applied to everyone.
  • Weather, heat and fatigue arrangements.
  • How to stop the job and who to tell.

Fields the JSA or SWMS has to carry

Task, location, workers involved, sequence of steps, hazards, controls and PPE against each step, competencies and licences for scaffold work, emergency arrangements, review triggers, and worker sign-on.

A Job Safety Analysis defines PPE, job steps, risks and controls in a risk matrix, which is the structure those fields hang off. Signatures are collected based on crew size, so the signature page should match the crew on site that morning, not the crew that was there when the document was written. If your records live in Safety Space, map these fields to the SWMS record before the first shift rather than after the first incident.

A safety checklist infographic comparing toolbox talk meeting points and JSA or SWMS template fields for construction sites.

Treat the fields as a structure to adapt, not a fixed form. A twelve-page JSA carrying forty generic hazards and no named control is worse than a single page naming the six things that will happen on today's lift, because the crew reads the second one.

Confirm the Procedure and Sign-On Before Work Starts

Approve the procedure only when the controls match the equipment on site. A housing trestle under a job written for heavy-duty scaffold is not an approvable method, however complete the PPE column looks. The same test applies to the saw and the lifting aid. If the written control is a wet cut and the brick saw on the slab is dry, hold the start.

Work through the gate in this order.

  1. Name the approver and the review date. An undated procedure with no named owner is still a draft, whatever the footer says.
  2. Walk the plant against the method. Scaffold type, working platform, brick or block saw, and lifting aid have to be the ones the procedure describes. If any of those changed overnight, send the procedure back for revision before anyone starts.
  3. Write the review triggers. A new scaffold type, a new brick or block, a change of cutting method, an incident or near miss, or a new crew each forces a fresh approval, not a note in the margin.
  4. File the pre-start and the open corrective actions with the job. Close-out evidence is the record of what was in place, not a reconstruction after an inspector asks.

Sign-on comes after that approval, on the version that names today's scaffold, saw and lift. A signature on yesterday's draft does not clear today's start.

I would not sign a procedure I have not stood under. The approver's job is to refuse the start when the written controls and the site disagree, then record that refusal against the job so the next crew does not inherit a stale approval.

Safety Space builds SWMS and JSAs with worker sign-on, so the procedure a crew signs is the same record the supervisor reviews. Toolbox talks, inspections and corrective actions sit against the same site record, which is what makes a close-out file something you can produce on request rather than reconstruct afterwards. Visit Safety Space to see how a bricklaying procedure moves from a template to a signed, dated record.

Ready to Transform Your Safety Management?

Discover how Safety Space can help you implement the strategies discussed in this article.

Explore Safety Space Features

Related Topics

Safety Space Features

Explore all the AI-powered features that make Safety Space the complete workplace safety solution.

Articles & Resources

Explore our complete collection of workplace safety articles, tools, and resources.